Phased Approach

The two phases of work to complete the full ambition for the centre are:

PHASE 1 (completed Nov 2015) – was focussed on creating the outdoor facilities at the new centre location allowing the club to transfer to the new site. The facilities comprise of 6 outdoor courts, 3 floodlit,  with a  car park and a temporary clubhouse, all accessible by wheelchair users. In addition a range of groundworks and fencing for the site were completed. A view of the site plan is available – Phase 1 Site Plan

SUBSEQUENT PHASE(S) – targeted to comprise the provision of the 4 indoor tennis courts along with the expansion of the car parking facilities and the landscaping of the grounds. Work will not commence until the finalisation of the funding from a number of sources i.e. Local Fundraising / LTA / SE. Further additions, dependent on available funding may comprise a ‘Clubhouse’ pavilion and Padel Tennis courts.

The final configuration of the centre may well be subject to change but a view of a possible site plan is available here  – Next(?) Phase(s) Site Plan.